Mawa End (North/Left Bank)
- length = 1.6 km
 - Concrete Block above water and riprap (Dumping of Bolders & Geobags) on dredged slope
 - Rock Required 8.5 Lacs tones
 - Dredging volume: 10.00 million m3
 
                    
                
                    
                
| Description | Unit | Location | Estimated Quantity | 
|---|---|---|---|
| Rock Rip-Rap | m3 | South Bank | 706,950 | 
| North Bank | 221,400 | ||
| Total | 928,350 | ||
| Geo-Bags | 800kg/Nos. | South Bank | 3,565,000 | 
| North Bank | 342,500 | ||
| Total | 3,907,500 | ||
| 125kg/Nos. | South Bank | 10,572,500 | |
| North Bank | 6,695,000 | ||
| Total | 17,267,500 | ||
| CC Block | 400×400×200/Nos. | South Bank | 367,641 | 
| North Bank | 123,233 | ||
| 400×400×300/Nos. | South Bank | 3,696,062 | |
| North Bank | 212,072 | ||
| 400×400×400/Nos. | South Bank | 7,582,546 | |
| North Bank | 1,284,694 | ||
| 600×600×600/Nos. | South Bank | - | |
| North Bank | 35,000 | ||
| CC Block Total | 13,301,248 |