Mawa End (North/Left Bank)
- length = 1.6 km
- Concrete Block above water and riprap (Dumping of Bolders & Geobags) on dredged slope
- Rock Required 8.5 Lacs tones
- Dredging volume: 10.00 million m3
Description | Unit | Location | Estimated Quantity |
---|---|---|---|
Rock Rip-Rap | m3 | South Bank | 706,950 |
North Bank | 221,400 | ||
Total | 928,350 | ||
Geo-Bags | 800kg/Nos. | South Bank | 3,565,000 |
North Bank | 342,500 | ||
Total | 3,907,500 | ||
125kg/Nos. | South Bank | 10,572,500 | |
North Bank | 6,695,000 | ||
Total | 17,267,500 | ||
CC Block | 400×400×200/Nos. | South Bank | 367,641 |
North Bank | 123,233 | ||
400×400×300/Nos. | South Bank | 3,696,062 | |
North Bank | 212,072 | ||
400×400×400/Nos. | South Bank | 7,582,546 | |
North Bank | 1,284,694 | ||
600×600×600/Nos. | South Bank | - | |
North Bank | 35,000 | ||
CC Block Total | 13,301,248 |