Present Status of the project

Time based work plan and achievement Upto July 2022

Project Name : Padma Multipurpose Bridge Project.
Ministry/Division/Agency: Ministry of Road Transport and Bridges, Bridges Division, Bangladesh Bridge Authority
Project Progress : 95.10%

Work Description as per work plan (major work)

Work start date according to work plan: November 2014
Work end date according to work plan: June 2022
Status:
All steel & bore Pile drive and river pier Column construction are Completed. All Steel Struss (Span) erected on the 42 Pier. all Pier column of Janjira and Mawa Viaduct are Completed, Total 2917 nos. Roadway deck slab, all are casting & erection completed and total 2,959 nos. Railway deck slab, all are casting & erection completed on the spans. 400KVA Power transmision Platform, Gas Pipeline & Lower Deck Walkway construction work is on going.
Percent Completed: 99.55%

Work start date according to work plan: November 2014
Work end date according to work plan: June 2022
Status:
Upto June 2022, major works of River Training Wlrks are completed in 6,170 metre. Total Dredging Work 5,94,80,000 cum. Completed Dredging Work 3,13,79315 cum. Total 800 kg gebag: 30,50,141 nos. Dumping completed till to date 22,69,389 nos. Total 125 kg geobag: 1,25,26,457 nos. Dumping Completed till to date: 45,08,409 nos. (including end termination berm). Total number of concrete block (dumping & placement): 93,83,602 nos. Casting completed : 62,08,139 nos. Dumping Completed: 27,94,787 nos. Placement completed 16,92,445 nos. Total quantity of Rock Rip-Rap: 9,10,675 cum. Already mobilized quantity in site: 8,43,955 cum. Dumping completed: 3,14,875 cum. At Janjira side: From sta.0-980m to sta.0-430m (550m) all permanent work completed. At South bank, From sta. 1+180~1+500 (1320m) in this section, all major permanent work is completed. After completion of embankment top work(HBB layer) & ongoing country side vetiver plantation, the full section will be completed. Also from sta. 4+900 to sta. 8+000 (2650) All permanent work completed excluding 3 offtakes (total 450m) & country side vetiver plantation. Dredging of offtakes has been completed. At 8+800~10+100 (1150m, excluding offtake # 1), all major permanent work has been completed.Also, in south bank downstream end termination berm construction is finished. Back filling inside berm also completed. At south bank section 1+500~1+800 (300m), dredging, final trimming, geobag dumping has been completed. Rock dumping is ongoing now. As a part of next year programm, Final trimming was completed & 800 kg geobag dumping has been started at section 10+100~10+500.Also bulk dredging ongoing at section 2+500~3+700 & at section 10+500~10+897. Also embankment dry filling/compaction work had been completed up to sta.2+700.Four large dredger & five dumping barge are working. Rock rip-rap mobilization & cc block production also ongoing. Total 3,50,000 cum geobag filling sand are stockpiled.At Mawa side geobag dumping work was completed at apron & slope (partial) from sta.0-500~0+900; in this 1400m area. Previously Two large scour hole was filled by pp bag and on layer 800kg bag was laid over this. Pond filling work was completed at upstream of north bank. Also embankment dry filling & compaction work was completed at north bank upstream. Embankment work at north bank downstream will be started soon. Top soil stripping work is ongoing at north bank upstream end termination.
Percent Completed: 95.20%

Work start date according to work plan: November 2014
Work end date according to work plan: June 2022
Status:Supervision of work is going on.
Percent Completed: 89%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2016
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2018 (including 1 year defect liability period)
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: August 2006
Work end date according to work plan: June 2023
Status:
   a) a) Munshigonj:Acquisition land = 329.76 hectares; Possession taken by PMBP = 320.04 hectares.
   b) Madaripur: Acquisition land = 1586.7562 hectares; Possession taken by PMBP =553.18 hectares
   c) c) Shariatpur: Acquisition land = 610.96 hectares; Possession taken by PMBP = 579.95 hectares


# Total proposed land for 03 districts =2693.21 hectares (As per RDPP);
# Total acquisition land for 03 Districts =2527.4762 hectares;
# Total Possession of land taken by PMBP in 3 districts =1453.17 hectares;
# Total requisition land for 03 Districts =139.07 hectares.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2023
Status:
   a) Tk. 761.28 crore additional grants have been handed over to the PAP up to June 2022.

    b) Total Plot allocated 3014 Nos. and 2997 Nos. plots have been handed over to the PAP which is recommended by the "Project Level Plot Allocation Committee" up to June 2022. Among them it has been handed over 787 Nos. of plots to Landless families without any cost. Moreover house development facility has been provided to the 1,058 nos. affected people.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2021
Status:
   a) 1,69,957 Nos. of tree plantation has been completed up to January 2021 in resettlement area, approach road and service areas. Tree plantation and the maintenance work of the planted trees are ongoing.
   b) MoU has been signed with Zoological Department of Dhaka University to stablish a Museum in the project area. 2,297 nos. sample of species has been collected and preserved till January 2021.
   c) For "Consultancy Services for Preparing a Comprehensive Documentation of Padma Multipurpose Bridge Project," negotiation has been signed between Impress telefilm and PMBP on 17/02/2016. According to contact the 1hr video recorded for the first 6 (six) month was received. Besides "One Hour Documentary Film" in Bangla & English version for the 2nd six month (October/2016 to March/2017), 3rd six month (April/2017 to September/2017), 4th six month (October/2017 to March/2018), 5th six month (April/2018 to September/2018) and 6th six month (October/2018 to March/2019) were also collected only Bangla version. Monthly progress report is being sent regularly.
   d) For "Consultancy Services on Biodiversity Conservation Programme of Padma Multipurpose Bridge Project," Contract agreement has been signed between Sodev Consult International Ltd. and PMBP on 31/12/2018. Work in ongoing as per contract agreement. Inception Report, Previous Study Review Report and Quartly (1st & 2nd) report submitted as per contract.
   e) Environmental Specialists along with Health & Safety Specialist are performing their job under the supervision of MSC and CSC-2 on the project sites.

Status:
Final Inception Report and Quality Assurance Manual submitted by Management Support Consultant (MSC) Service Contract of Padma Multipurpose Bridge Project. Work is ongoing. Percent Completed: 100%

Download time based work plan and fast track project progress July 2022 (Bangla version) :  microsoft word logo

Download time based work plan and fast track project progress July 2022 (English version) :  microsoft word logo