Present Status of the project

Time based work plan and achievement Upto December, 2017

Project Name : Padma Multipurpose Bridge Project.
Ministry/Division/Agency: Ministry of Road Transport and Bridges, Bridges Division, Bangladesh Bridge Authority
Project Progress : 50.00%

Work Description as per work plan (major work)

Work start date according to work plan: November 2014
Work end date according to work plan: November 2018
Status:
River Span of Main Bridge’s total Pier 40 Nos., Total Steel Pile 240 Nos., 10 Completed Bottom Section Driving, 88 Completed Top & Bottom Section Driving, 4 Completed Pier Column and P1 & P42 Total Pier 2 Nos., Total Bored Concrete pile 28 Nos., 16 Completed Top & Bottom section driving. Janjira Viaduct Total Pier 40 Nos., Total Bored Concrete Pile 193 Nos., 193 Completed Top & Bottom section section driving, 4 Completed Pier Column (Partially casting of column no. N-24 (3th lift), N-28 (2nd lift)) and Mawa Viaduct Total Pier 37 Nos., Total Bored Concrete Pile 172 Nos. 64 Completed Top & Bottom section driving, Truss Fabrication: Total Number of Truss span 41. 11 Reached Span Number at Construction Site, 7 Fabricated Span Number at Construction Site, 1 Span Erection on Pier P37 & P38 and Fabrication Work is ongoing for the rest of four & another two nos. relevant work is about to end.Completed Construction of Steel member from using steel plate at Workshop in China= 12 Nos (Staying at Mawa ghat for Shipment) and another 7 nos. construction work is on going.
Percent Completed: 53.00%

Work start date according to work plan: November 2014
Work end date according to work plan: November 2018
Status:
Mobilization of equipment such as various sizes rock, stone chips, Sylhet sand, cement and other construction materials is going on. Casting of 30,76,227 Nos. concrete blocks out of 1,33,01,248 Nos. has been completed. Dumping of 27,47,791 nos. Geo-bags out of 2,12,75,000 Nos. has been completed. At Mawa site out of 1.8 km river training work from chainage -500m to +900m (1.4 km) 800kg Geo-bag damping has been completed at 5 layers in lunching apron and 800kg geo bag damping have been completed. Besides at Mawa site Scour Holes (Void 1 & Void 2) at slope were filled and 125 kg Geo-bag damping work has been completed above them at 2 layers. Moreover 8 nos pond filling work have been completed at embankment zone. Compaction and dry filling from chainage -0+160m to 4+480m at embankment zone are ongoing. At Jajira site trial section from chainage -980m to 0-400m (580m) 800kg geo bag damping have been completed at 5 layers in lunching apron and 125kg geo bag damping have been completed at 3 layers. Besides at Jajira site trial section from chainage 0-500m to 0-700m (200m in total) rock damping work has been completed upto 45,937 cubic meters and CC block damping has been completed upto 1,13,354 nos. Sediment removal, rock dumping up gradation and anchor beam construction of incomplete trial section are ongoing now. Besides at Jajira site embankment work from 1+650m to 2+700m is ongoing. Slope Trimming at the countryside of the embankment in being continued and sandy loam placement is also ongoing. At Janjira site from chainage 4+900m to 6+500m (1.2 km) bulk dredging and trimming have been completed. At present from chainage 5+300m to 6+000m 800kg Geo-bag damping is ongoing on apron and slope simultaneously. Moreover At Janjira site from chainage 0+100m to 1+100m bulk dredging is completed and final trimming work is ongoing. In the meantime, casting of 102,62,632 nos CC half bricks out of 5,34,50,500 nos has been completed and the rest of work is ongoing. Besides 14,54,800 nos CC half Bricks dumping was completed.
Percent Completed: 34.40%

Work start date according to work plan: November 2014
Work end date according to work plan: November 2019
Status:Supervision of work is going on.
Percent Completed: 59%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2016
Status: Approach Road = 10.637 km, Service Road =9.589 km, link road=5.495km and Connecting Road =4.495 km construction work is ongoing. Construction work of 5 nos Bridge, 20 nos Culvert, 8 nos Underpass as well as Toll Plaza, Police Station & Fire Station is also being continued.
Percent Completed: 99.75%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2018 (including 1 year defect liability period)
Status: Supervision of work is going on.
Percent Completed: 96%

Work start date according to work plan: August 2006
Work end date according to work plan: June 2015
Status:
   a) a) Munshigonj:Proposed land =412.70 hectares; Acquisition land = 331.25 hectares; Possession taken by PMBP = 319.91 hectares.
   b) Madaripur: Proposed land = 1710.88 hectares; Acquisition land = 1100.41 hectares; Possession taken by PMBP =549.76 hectares
   c) c) Shariatpur: Proposed land = 741.46 hectares; Acquisition land = 591.56 hectares; Possession taken by PMBP = 579.74 hectares


# Total proposed land for 03 districts =2865.04 hectares;
# Total acquisition land for 03 Districts =2023.22 hectares;
# Total Possession of land taken by PMBP in 3 districts =1449.41 hectares.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2020
Status:
   a) Tk. 622.28 crore additional grants have been handed over to the PAP up to November/2017.

   b) b) 2452 Nos. plots have been handed over to the PAP which is recommended by the “Project Level Plot Allocation Committee” up to November/2017. Among them it has been handed over 631 Nos. of plots to Landless families without any cost. Moreover house development facility has been provided to the 511 nos. affected people.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2020
Status:
   a) 1,57,757 Nos. of tree plantation has been completed up to November/2017 in resettlement area, approach road and service areas. Tree plantation and the maintenance work of the planted trees are ongoing.
   b) MoU has been signed with Zoological Department of Dhaka University to stablish a Museum in the project area. 1260 nos. sample of species has been collected and preserved till November/2017.
   c) For 'Consultancy Services for Preparing a Comprehensive Documentation of Padma Multipurpose Bridge Project,' negotiation has been signed between Impress telefilm and PMBP on 17/02/2016. According to contact the 1hr video recorded for the first 6 (six) month was received. Besides 'One Hour Documentary Film' in Bangla version for the 2nd six month (October/2016 to March/2017) and 3rd six month (April/2017 to September/2017) were also collected. Monthly progress report is being sent regularly.
   d) Environmental Specialists along with Health & Safety Specialist are performing their job under the supervision of MSC and CSC-2 on the project sites. A training session was arranged on 'Environment, Health and Safety' at SA-1 in 6-8 November, 2017.

Status:
Final Inception Report and Quality Assurance Manual submitted by Management Support Consultant (MSC) Service Contract of Padma Multipurpose Bridge Project. Work is ongoing. Percent Completed: 41%

Download time based work plan and fast track project progress December 2017 (Bangla version) :  microsoft word logo

Download time based work plan and fast track project progress December 2017 (English version) :  microsoft word logo